The Village will be completing a project to reconstruct Lake Meadow Drive from Lighthouse Drive to Main Street. The work will include a removal of the top portion of the road’s existing pavement and paving the road with new asphalt.  Drainage improvement work will also be done in the ditch areas along Pinewood and Sprucewood Courts.

The Village’s contractor, Payne & Dolan’s tentative schedule for the work will be as follows:

    • July 25: Traffic control installation (signage)
    • Week of July 27: Drainage work including ditch grading, small rip rap, culvert cleaning and inlet protection.
    • Week of August 3: Removing existing road surface and prep for new asphalt.
    • Week of August 10: Adjust manhole covers and paving.
    • Week of August 17: Shouldering and lane striping

Please note that these dates are currently tentative, and are weather dependent.  The contractor and Village have been in contact with representatives from the Prairie School regarding traffic concerns for the school.  Our hope is to have the majority of the road work completed before school begins on August 18.

There will be no permanent road closures during the work, however due to construction crews on the road, there may be slight travel delays. There will also be a week of time between the removal of the existing pavement and the construction of new pavement, where the road will be rough.  We ask for your patience when traveling the road and urge caution when driving through the construction zone.

If you have any questions or concerns please contact the Village Office at 262-639-3524 or info@windpoint.org.